NJWB December 8th, 2021
Middlesex County Utilities Authority (MCUA) recently closed on a $17,800,000 loan with the New Jersey Water Bank to complete rehabilitation of its central treatment plant, originally constructed in the 1970s. The project consists of structural and electrical rehabilitation of the two primary tank traveling bridges; the replacement of the collector mechanisms in the remaining three final clarifier units including recoating two of the newer (1990s) mechanisms; and the replacement of the collector mechanisms in the remaining five gravity thickener units. This project will allow the Authority to continue to meet the Plant's effluent water quality permit requirements.
For more information, contact the New Jersey Infrastructure Bank at (609) 219-8600.
Similar Stories See All Stories
3131 Princeton Pike, Building 4 Suite 216
Lawrenceville NJ, 08648 T. 609 219 8600